Phase 1 : Authority approvals – Approved
Phase 2 : Earthworks – 80% complete
Phase 3 : Sewer & Drainage – Construction of sewer and drainage services – 80% complete
Phase 4 : Water & road excavation – Construction of initial road works and installation of water – End of June 23
Phase 5 : Electrical, Gas & Telecommunications – Installation of gas, electrical and telecommunication services –End of July 23
Phase 6 : Road pavements & concreting – Construction of road krebs, finalisation of road construction and the installation of footpaths and topsoil – End of August 23
Phase 7 : Compliance inspections – Inspections and signoffs by the Council and relevant service authorities to achieve a Statement of Compliance – End of September 2023
Phase 8 : Title registration – Registration of lots with Land Titles Office. Certificates of Title are issued for each individual lot followed by Settlement of lots within 14 days – Registration Mid of November 2023