Please find below the update for Limestone Estate Stages 3 & 4
Phase 1 :
Authority approvals – Approved
Phase 2 :
Earthworks – 100% Completed
Phase 3 :
Sewer & Drainage – Construction of internal sewer and drainage services – 10% Completed
Phase 4 :
Water & road excavation – Construction of initial road works and installation of water – July 24
Phase 5 :
Road pavements & concreting – Construction of road Krebs, preparation of road construction and the topsoil – Aug 24
Phase 6 :
Electrical, Gas & Telecommunications – Installation of gas, electrical and telecommunication services – Sep 24
Phase 7 :
Compliance inspections – Inspections and signoffs by the Council and relevant service authorities to achieve a Statement of Compliance – Oct 24
Phase 8 :
Title registration – Registration of lots with Land Titles Office. Certificates of Title are issued for each lot followed by Settlement of lots within 14 days – Early Nov 2024